Content
Financial Perspective: Step 1 - Collect key financial pressures
The Sponsor completes this step in three parts in consultation with Integrated Project Teams:
- Key Financial Pressures
- Potential Capability Management Measures
- Potential Options.
The data is collected from the “Feedback Form” from the 1* level Screenings for a Planning Round and through records of screening meetings and notes.
Key Financial Pressures
The following table shows a template for collecting this data:
Major Issues |
Way Ahead |
Impact on Platform/Capability |
| |
|
|
Potential Capability Management Measures
The following table shows a template for collecting this data:
Project Line Receiving Resource (Type of DEL ) |
Profile of Funds to be Moved |
Project Line(s) Surrendering Resource (Type of DEL ) |
|
|
|
Potential Options
The following table shows a template for collecting this data:
Major Issues |
Way Ahead |
Impact on Platform/Capability |
| |
|
|
Other factors to consider
How confident is the Director of Equipment Capability (DEC) about the fidelity of the re-costed profiles for P9 lines (at Project level) and Equipment Support lines (at Project level, if available or at IPT level)? Do the re-costed profiles include a reasonable provision for risk? |
What are the key assumptions underpinning the re-costed profiles? |
Are there any significant gaps in the data and what actions do the Capability Management Group (CMG) and hosted Capability Planning Groups (CPGs) propose to take to remedy this? |
What is the overall financial position for the CMG, in terms of its hosted CPGs and what are the key financial pressures (significant variances) that the CMG faces? These will need to be presented at project or programme level in terms of:
- The financial shortfall as an amount (£m) in terms of expenditure limits (RDEL and CDEL), the years impacted and the key factors driving that variance.
- The impact of returning that project or programme to baseline (and beyond), including the level of ‘pain’ associated with those actions.
- The impact of the financial shortfall on planned capability, if not addressed, and the associated level of risk to Defence and Equipment Capability Customer (ECC) objectives.
|
Has any significant incoherence been identified across other Defence Lines of Development (DLoD) and what are the Centre - including Resource and Plans (RP) - and User perspectives on this? |