Content
Requirements and Acceptance Management Plan (RAMP) Structure
A Requirements and Acceptance Management Plan (RAMP) covers:
- Introduction and overview
- Planning for Requirements
- Planning for Acceptance
- Requirements and Acceptance Process
- Products:
- User Requirements Document (URD)
- Systems Requirements Document (SRD)
- Integrated Test Evaluation and Acceptance Plan (ITEAP) .
Introduction and overview
This should set out the principles of how the requirements and acceptance activities are going to be completed. Reasons for why a project does not comply with the guidance should be highlighted.
Planning for Requirements
- Who will carry out the process of identifying the Requirements?
- Will there need to be any third party or specialist contractor involvement? If so, describe what contractual mechanism will be used to enable this.
- How will the identified Requirements be prioritised, and what role will stakeholders play in agreeing this?
- Who will confirm that the Measures of Effectiveness (MoEs) and Measures of Performance (MoPs) reflect planning assumptions and capability need?
Planning for Acceptance
- Who will carry out the process of Acceptance, and what contractual mechanism will be used to enable this?
- Has the scope and type of the evidence to be collected been agreed with key stakeholders, and confirmed with relevant technical experts as sufficient?
- When will the testing be completed, and will this be representative of the final product?
- Will all products be tested, or will this be limited to a percentage of products or factory tests of component performance?
- How will pass / fail criteria be established as part of any test plan, and how will successful testing be planned and scheduled to inform the acceptance process?
Requirement and Acceptance Process
This section should set out the process to follow from requirements to acceptance:
- Scoping of Requirement
- Requirements elicitation (Systems Engineering, Expert Panel)
- Requirements prioritisation
- Requirements testing
- Acceptance case construction
- Process of acceptance agreement
- Final acceptance.
Products
The RAMP should identify what products will be produced to support the Requirements and Acceptance process.
As a minimum they should include: