Integrated Test, Evaluation and Acceptance (ITEA) Process: the Six TasksThis guidance is for those acting in the ITEA Manager role and describes how to define the ITEA products. The six tasks detailed here, form the ITEA Process . The focus of the process is the ITEAP, associated ITEA Schedule and the Validation, Verification and Requirements Matrix (VVRM). Further information on ITEA principles is also available. The six tasks are:
The process is iterative and the ITEA products should be reviewed throughout the project lifecycle, so that changes are recorded and the impact of trade off decisions are assessed. Task 1 - Plan the approachPlan the approach this is set out in the acceptance strategy documented in the Requirements and Acceptance Management Plan (RAMP). Task 2 - Define the Validation and Verification criteriaAs the user requirements document (URD) and system requirements document (SRD) are developed, the methods for validation and verification criteria should be recorded. This will be used as the basis for ITEA planning. Early identification of trials facilities should be planned with the DE&S TEST IPT. Task 3 - Detail the ITEAPStep 1 – Identify . Identify sources of need for Test and Evaluation building on the URD and SRD validation and verification methods. The ITEA process addresses:
Early planning is required for:
Step 2 – Scope . Scope the outline test and evaluation requirement for individual sources of need. As the URD and SRD start to evolve and solution options reduce, review the validation requirements to ensure their continuing appropriateness. Identify the need for military exercises and range utilisation where long term planning is required. Baseline the validation requirements with the rest of the URD at Main Gate. If the SRD is baselined at Main Gate and a negotiated test method differs from the SRD criteria then a formal approval will be required by submission of a Review Note. The scope will include:
Step 3 – Achievability - Compare estimated cost (including the production of test articles and development of facilities) to budget. Compare schedule to critical project milestones and demand for resources (test facilities, government furnished assets (GFX) and test articles) to availability. Resolve problems, and inform risk management as appropriate. Step 4 – Risk Assessment - Within the context of project risk management, perform a risk assessment on the draft ITEAP – areas to consider are:
Develop risk mitigation actions:
Step 5 – Consolidate . Consolidate the sets of tests and their implications as scoped in Step 2, to form a draft ITEAP , ITEA schedule and VVRM.
Step 6 – Document . Document and cross reference to reflect the (draft) ITEAP in the:
Step 7 - Develop Implementation Processes - establish formal collaborative processes or procedures in order to agree administration of T&E activity across organisational boundaries. These might embrace areas such as:
Ensure that there is an adequate process in place to progress delivery of the non-equipment DLoD of Military Capability (MC) into validation testing. Step 8 - Optimise the ITEAP and obtain stakeholder endorsement - Reflect the conclusions of the achievability and risk assessment in the ITEAP, and obtain stakeholder agreement to it including regulatory stakeholders such as:
Baseline and publish the ITEAP and Schedule maintaining it under configuration control. Ensure that the SRM, Asset and Contract Delivery Schedules and other dependent plans remain aligned with the ITEAP and ITEA Schedule. Task 4 – Execute the ITEAPBook trials facilities, carry out tests and collate result set as acceptance evidence in the VVRM. Manage the DLoDs progress and record within the ITEAP. Task 5 – Evidence managementAnalyse the acceptance evidence and make recommendations. Step 1 Within the ITEAP update the progress of the overall development including the other DLoDs. This should highlight any issues such as long term needs for test facilities and dependencies on other projects and programmes. Step 2 The acceptance evidence is built up in the VVRM to collate the test results. Step 3 Assessment - Analyse and assess the acceptance evidence contained in the reports from the VVRM. Step 4 Record the outcome of the tests (pass/fail) for compliance or non-compliance. Step 5 Following assessment of the results agreement is required between the stakeholders (Sponsor and user). These decisions may be influenced by political and operational pressures that will need to be identified in risk mitigation strategies. Where agreement is not achieved the alternative options include:
Step 6 Following the assessment of the tests a recommendation is made on acceptance to the acceptance authority. Task 6 – DeclarationA recommendation to the acceptance authority is required for the following milestones:
Test and evaluation recommendation can also aid the customer in the down selection to the preferred solution and mitigation of risk at the assessment stage.