Content
Designated User and Joint User Tasks
This table summarises the Users tasks through the CADMID acquisition lifecycle.
| Step / Stage |
Lead |
Designated User Tasks |
Joint User Tasks |
| Designated User answerable to Single Point of Accountability (SPA). |
Develop Concepts of Employment (CONEMP) drawing provenance from Applied Concepts. Agree Key User Requirements (KURs) and User Requirement Document (URD).
Represent User position at Capability Planning Groups (CPGs).
Establish Capability Integration Working Group (CIWG) and develop Capability Integration Plan (CIP).
Provide Defence Lines of Development (DLoD) Cost Of Ownership (COO) data as required and support production of TLMP. |
Provide Joint User input to CONEMP advise whether it requires Joint endorsement by JCUMG.
Provide designated User inter-service and inter-environment advice.
Provide designated User advice on Joint requirements. |
| Designated User answerable to SPA. |
Deliver endorsed CONEMP ahead of Main Gate BC drawing provenance from Applied Concepts.
Represent User position at CPGs
.Manage CIWG and CIP.
Support Programme Board acceptance work, agree Capability Trades with SPA, ensure any excess/shortfalls against CONEMP are recorded.
Provide DLoD COO data as required and support production of TLMP. |
Provide Joint User input to CONEMP lead on achieving 1* Joint endorsement by JCUMG if applicable.
Provide designated User inter-service and inter-environment advice.
Provide designated User advice on Joint requirements. |
| Designated User answerable to SPA |
Migrate to CONUSE ahead of ISD drawing provenance from CONEMP and Applied Concepts.
Represent User position at CPGs
. Manage CIWG and CIP.
Support Programme Board acceptance work, agree Capability Trades with SPA, ensure any excess/shortfalls against CONEMP are recorded in CONUSE.
Support TLMP and ensure DLoD STP funding is secured |
Provide Joint User input to CONUSE lead on achieving 1* Joint endorsement by JCUMG if applicable.
Provide designated User inter-service and inter-environment advice.
Provide designated User advice on Joint requirements. |
| Designated User answerable to SPA |
Deliver endorsed CONUSE ahead of ISD drawing provenance from Applied Concepts.
Represent User position at CPGs. Engage in capability integration activity in support of the Sponsor.
Support Programme Board acceptance work, agree acceptance criteria.
Record performance excess/shortfalls in CONUSE.
Support TLMP and ensure DLoD STP funding is secured. |
Provide Joint User input to CONUSE lead on achieving 1* Joint endorsement by JCUMG if applicable.
Provide designated User inter-service and inter-environment advice.
Provide designated User advice on Joint requirements. |
| Designated User |
Review endorsed CONUSE drawing provenance from Applied Concepts.
Reflect Capability upgrades.
Represent User position at CPGs. Engage in capability integration activity in support of the Sponsor. Designated User Declare ISD / FOC.
Co-ordinate Capability Upgrade opportunities with SPA.
Record performance excess/shortfalls in CONUSE.
Manage process to deliver FE@R Support TLMP and ensure DLoD STP funding is secured. |
Provide Joint User input to CONUSE updates.
Provide designated User inter-service and inter-environment advice.
Provide designated User advice on Joint requirements. |
| SPA |
Represent User position at CPGs. |
Advise designated User on Joint considerations that impact upon disposal. |
Change History
Change History
The AOF has been updated to Version 2.0.0 on 1st April 2008 following the introduction of the main content in the tactical layer. In addition small changes have been added to the Operational layer. Individual document Change History pages will detail any changes other than minor editorial amendments.
- 1 November 2009
- Minor amendments made for Plain English review.
- 1 July 2008
- Table amended to align with the CADMID lifecycle.
- 1 October 2007
- New content – User role in the development of Defence Capability.